How to File a RERA Complaint in West Bengal

By Advocate Panchanand Shaw, Bar Council of West Bengal · Published 25 Nov 2026 · Real estate law

A RERA complaint is filed under Section 31 of the Real Estate (Regulation and Development) Act 2016 with the regulatory Authority or the Adjudicating Officer, according to the relief claimed. In West Bengal the Authority is the West Bengal Real Estate Regulatory Authority, the complaint is made in the prescribed form with a fee of one thousand rupees, and the Authority is required to dispose of the matter within sixty days.

Where a RERA complaint goes

The Real Estate (Regulation and Development) Act 2016 gives an aggrieved homebuyer two doors. Section 31 allows any aggrieved person to file a complaint with the regulatory Authority or with the Adjudicating Officer, depending on the relief sought. In West Bengal the Authority is the West Bengal Real Estate Regulatory Authority, and the complaint is filed under Section 31 read with the relief provision you are relying on — most often Section 18 for delayed possession or refund.

The division between the two is worth understanding before you draft anything. The Authority decides questions of refund, interest for delay and penalties. The Adjudicating Officer adjudges compensation — a money sum claimed on account of the promoter's failure to comply with a duty under the Act. Filing a compensation claim before the wrong forum is one of the commonest reasons a complaint is returned for correction.

Why registration of the project matters first

RERA works because projects must be registered before they are sold. Section 3 requires a promoter whose project involves land exceeding five hundred square metres, or more than eight apartments, to register with the Authority before advertising, booking or offering any apartment for sale. Section 4 sets out the application for registration and the disclosures that go with it. Once registered, the registration number on the Authority's website is the single most useful fact in any complaint, because it ties the promoter, the project and the complaint together.

Before filing, check on the West Bengal Real Estate Regulatory Authority's website whether your project is registered, and what possession date the promoter declared. If the project is not registered, the complaint changes character: instead of a Section 18 claim you may have a Section 59 complaint that the promoter sold without registration, which carries its own penalty. In that case a consumer complaint is often the better route for recovering your own money.

When a RERA complaint lies

Complaints are usually brought on one of these grounds:

How the complaint is filed

In West Bengal the complaint to the Authority is made in the prescribed form — Form 'M' under the West Bengal Real Estate (Regulation and Development) Rules 2021 — accompanied by a fee of one thousand rupees, payable by demand draft on a scheduled bank or by electronic transfer. The complaint may be filed online through the Authority's portal or physically at its office in Kolkata.

The papers filed at the start decide the case, so assemble them first:

Where the complaint relies on electronic correspondence, remember the admissibility rule. Under Section 63 of the Bharatiya Sakshya Adhiniyam 2023, which replaced Section 65B of the Indian Evidence Act, a copy of an electronic record is admitted only with the certificate in the statutory form. Preserve the device or the account from which the messages came, and keep that certificate ready before the record is offered in evidence.

What happens after filing

The Authority issues notice to the promoter, who files a reply. A hearing follows, usually a summary one in which both sides are heard, and the Authority passes a reasoned order. Section 29 requires the Authority to dispose of the matter as expeditiously as possible and, in any event, within sixty days of receipt, recording reasons in writing if it cannot.

In a straightforward delayed-possession case the order usually directs possession by a fixed date with interest for the delay, or refund of the amount paid with interest — whichever route the allottee has chosen and pleaded. The choice therefore belongs in the complaint, not to be left open for the hearing.

What you can claim

ReliefProvision
Refund of the amount paid with interest, where the allottee withdraws because possession is not givenSection 18
Interest for every month of delay, where the allottee chooses to stay in the projectSection 18
Compensation for loss caused by the promoter's contraventionAdjudicating Officer under the Act
Penalty for selling without registrationSection 59 — up to ten per cent of the estimated cost of the project
Penalty for false information in the registration applicationSection 60
Rectification of structural defects within five years of possessionSection 14
Revocation of the project's registration in serious casesSection 7

The refund and the delay interest are payable at the rate the State rules prescribe. In West Bengal, Rule 17 of the 2021 Rules fixes the rate as the prime lending rate of the State Bank of India plus two per cent, and the West Bengal Real Estate Appellate Tribunal has held that, the Prime Lending Rate having been replaced, the calculation should use the State Bank's Marginal Cost of Lending Rate plus two per cent. Because the rate follows the bank's benchmark, it is worked out at the time of the order, not at the time of booking.

If the order is not obeyed

An order of the Authority is enforceable, and that is what makes it worth having against a promoter who ignores correspondence. Where a promoter fails to pay interest, penalty or compensation, Section 40 allows the sum to be recovered as an arrears of land revenue, which in practice means recovery through the District Magistrate.

Appeals

An order of the Authority or the Adjudicating Officer can be challenged before the Real Estate Appellate Tribunal, established under Section 43. Section 44 requires the appeal to be filed within sixty days of receipt of the order, with a discretion in the Tribunal to condone delay for sufficient cause, and directs the Tribunal to dispose of the appeal, as far as possible, within sixty days. Where a promoter appeals, the appeal is not entertained unless the promoter has first deposited at least thirty per cent of the penalty, or of the amount payable to the allottee. An order of the Tribunal can be taken further to the High Court.

RERA or the consumer commission

A homebuyer often has both a RERA remedy and a consumer remedy, and the choice matters.

RERAConsumer commission
Governed byReal Estate (Regulation and Development) Act 2016Consumer Protection Act 2019
Where filedWest Bengal Real Estate Regulatory AuthorityDistrict Commission up to fifty lakh rupees; State Commission between fifty lakh and two crore; National Commission above two crore
Typical strengthDelay, refund and possession against a registered project, with penalties for the promoterCompensation for mental agony, deficiency in service and unfair trade practice

Running both at once on the same cause of action is a risk, because the same grievance contested in two forums can attract an objection that parallel proceedings are not permissible. Decide the primary forum at the outset and carry the case to a conclusion there.

Who can file, and against whom

Section 31 is wide. Any aggrieved person may complain — the allottee who booked the apartment, but also an association of allottees or a recognised voluntary consumer association acting for the buyers. The complaint may be brought against the promoter, against another allottee, or against a real estate agent, depending on who has contravened the Act.

This matters where a single buyer cannot afford the effort of a long case. An association of allottees in a stalled project can file one complaint covering the grievances of many flat buyers, and the relief is then worked out across the group rather than flat by flat. That route needs the group to be organised and the common facts to be the same.

Mistakes that get a complaint returned

Most complaints are not lost on the law but on the paperwork, and the recurring faults are predictable.

A complaint drafted with the correct route, a clear computation and complete documents moves faster and is harder to deflect.

RERA and a civil suit

A RERA complaint is not the only remedy a homebuyer has. An agreement for sale is a contract, and a buyer who wants the flat rather than the money can sue for specific performance in the civil court. A buyer who has been cheated can, in a proper case, invoke the criminal law rather than the regulatory route.

The practical reason to prefer RERA for a registered project is speed. The Authority is designed to decide within sixty days and can enforce its order through the District Magistrate, while a civil suit carries the ordinary delays of litigation. A civil suit remains relevant where the claim is outside RERA — for instance against a person who was not a promoter within the Act, or where the relief sought is a declaration of title that the Authority cannot grant. Choosing the wrong forum at the start is expensive, and the choice should follow the relief you actually want.

How this office handles RERA complaints

We check the registration and the agreement, quantify the delay and the interest, draft the complaint and the affidavit, and file it before the West Bengal Real Estate Regulatory Authority. Where the facts support a consumer complaint instead, we say so before filing. The relevant practice pages are property disputes and consumer complaints, and you can begin with a review of your agreement and receipts through the contact page.

Need help with a cyber crime matter?

Tell me what happened and I will tell you what to file, where, and by when. First conversation is free.

Call +91-9403890320

Frequently asked questions

Can I file a RERA complaint online in West Bengal?

Yes. The West Bengal Real Estate Regulatory Authority accepts complaints online through its portal and also physically at its office. Register as a complainant, select a complaint against the promoter, enter the project registration number and the relief claimed, upload the agreement and payment records, and pay the fee. Note the complaint number that is generated, because it is what you quote in every follow-up.

What is the fee for a RERA complaint in West Bengal?

Under the West Bengal Real Estate (Regulation and Development) Rules 2021 the complaint to the Authority is accompanied by a fee of one thousand rupees, payable by demand draft on a scheduled bank or by electronic transfer. A complaint filed before the Adjudicating Officer carries its own fee fixed by the rules. Neither is the ad valorem court fee charged in a civil suit.

How long does the Authority take to decide a complaint?

Section 29 of the RERA Act requires the Authority to deal with the matter as expeditiously as possible and, in any event, to dispose of it within sixty days of receipt, recording reasons in writing if it cannot. The sixty days is a statutory target, not a guarantee, and contested matters and adjournments push the practical timeline beyond it.

Can I claim both possession and compensation?

Possession with interest for the delay is claimed from the Authority, while compensation for loss caused by the promoter is adjudged by the Adjudicating Officer. They are two routes and the reliefs should be pleaded before the correct forum. A complaint that mixes them without care can be partly returned, so state clearly which relief you seek from which authority.

What if my project was never registered at all?

Then the promoter sold in contravention of Section 3, and Section 59 allows a penalty up to ten per cent of the estimated project cost. For recovering your own money, however, an unregistered project is often better pursued as a consumer complaint under the Consumer Protection Act 2019, because there is no registration record to anchor a Section 18 claim before the Authority.

Can I go to RERA and the consumer court together?

Running two proceedings on the same cause of action at the same time is risky and can attract an objection that parallel proceedings are not permissible. Choose the forum that fits the relief: RERA for delay, refund and possession against a registered project, and the consumer commission where the claim is essentially one of compensation and deficiency of service.

What interest rate applies to a delayed possession or refund?

Rule 17 of the West Bengal Real Estate (Regulation and Development) Rules 2021 fixes the rate as the prime lending rate of the State Bank of India plus two per cent. The West Bengal Real Estate Appellate Tribunal has held that, the Prime Lending Rate having been replaced, interest should be computed on the State Bank Marginal Cost of Lending Rate plus two per cent. The figure moves with the bank benchmark.

What happens if the builder does not obey the RERA order?

The order is enforceable. Under Section 40 of the Act a sum ordered against a promoter is recoverable as an arrears of land revenue, which the Authority enforces through the District Magistrate. If the promoter appeals, Section 43(5) requires a pre-deposit of at least thirty per cent of the penalty or of the amount payable to the allottee before the appeal is heard.

Information for general guidance only and not legal advice. Provisions cited follow the Information Technology Act 2000, the Bharatiya Nyaya Sanhita 2023 and the Bharatiya Nagarik Suraksha Sanhita 2023.